This is the endgame schedule for April 2019 Iteration.

Schedule

Note: The Insiders build needs to be in the wild for 24 hours before we can enter the last phase of the endgame.

Monday 05/06
  • Run OSS tool Martin Aeschlimann (@aeschli)
    • The LCA review of the ThirdPartyNotices.txt files is not needed anymore
  • Code freeze at 5pm PT
  • Ensure we have a green build on all platforms at 5pm PT
  • All test items contain test meta data by 5pm PT and sufficiently comprehensive test descriptions by 8am CET
  • Update your availability for testing here - https://vscode-tools.azurewebsites.net/
Tuesday
  • Test plan items assigned (using https://vscode-tools.azurewebsites.net/)
    • Run the tool multiple times to balance load if test items come in later and assignments are already made
  • All closed feature-requests either have a verification-needed or on-testplan tag
  • Test build starts at 7am CET
  • Test plan ready by 8am CET
  • Testing
  • Verification needed
Wednesday
  • Testing
  • Remind team members to assign issues that they intend to fix to the current milestone
  • Fixing (self-assigned, milestone assigned)
  • Verification
Thursday
  • Fixing (scrutiny sets in - major bugs only - to be discussed in stand-up meeting, labeled as candidate)
  • Verification
Friday
Friday/Monday
Monday - Wednesday

Note: The Insiders build needs to be in the wild for 24 hours before we can enter the last phase of the endgame.

Wednesday/Thursday

Metadata

Metadata

Labels

endgame-planVS Code - Next release plan for endgame

Type

No type

Projects

No projects

Milestone

Relationships

None yet

Development

No branches or pull requests

Issue actions