Why this matters
Post-release planning found 196 open issues without a release milestone. Some are true backlog, but the new release process needs explicit release buckets for work that belongs to versioned trains.
Evidence
gh issue list --state open --limit 500 grouped by milestone after v18.1.2 showed:
(none): 196 open issues
v19.0.0: 13 open issues after v19 activation
v20.0.0: 16 open issues
v21.0.0: 11 open issues
Done when
- All open issues have been reviewed for release targeting.
- Issues that belong to planned release trains have a version milestone.
- Issues that are intentionally backlog-only remain unmilestoned with
priority:later and correct type/status/area labels.
- Any stale, duplicate, or already-satisfied issues are closed with a short evidence note.
Why this matters
Post-release planning found 196 open issues without a release milestone. Some are true backlog, but the new release process needs explicit release buckets for work that belongs to versioned trains.
Evidence
gh issue list --state open --limit 500grouped by milestone afterv18.1.2showed:(none): 196 open issuesv19.0.0: 13 open issues after v19 activationv20.0.0: 16 open issuesv21.0.0: 11 open issuesDone when
priority:laterand correct type/status/area labels.